Traffic Advisories

Print
Press Enter to show all options, press Tab go to next option

NNOWe understand your time is precious, so we are planning to provide you with up to date information so you have greater control over your drive, with insights that allow you to discover the best route so you can save time.  

We are bringing you the traffic advisory weekly updates on currently known roadway and related projects, and private utility work (based on street encroachment permits), to provide you an opportunity to look ahead, plan your travel times and check delays due to various street activities.   

Tahoe Drive at Ralston Ave

March 18- March 22

8:00 AM - 5:00 PM

Lane closures are only permitted 9AM-3PM, Monday through Friday

The contractor will be working on the traffic signal poles fronting the Ralston Middle School this week. The contractor may need to close off a lane going both East and West on Ralston Ave. Traffic control will be in place continuously during this period.

Motorists can make trips a little safer by remembering the following work zone safety tips.

  • Do not speed in work zones; obey the posted speed limits.
  • Stay Alert! Expect the unexpected.
  • Watch for workers; drive with caution.
  • Don't change lanes unnecessarily.
  • Avoid using mobile phones while driving in work zones
  • Be especially alert at night while driving in work zones.
  • Expect delays, especially during peak travel times.
  • Allow ample space between you and the car in front of you.
  • Anticipate lane shifts, and merge when directed to do so.
  • Be Patient!

 

 

Monte Cresta Dr and Alhambra Dr 

March 18- March22

8AM – 5PM

Paving subcontractor will be on the 2800 block of Monte Cresta Drive and Alhambra Drive performing street and sidewalk restoration. Work hours are 8AM-5PM Monday, March 4th thru Tuesday, March 5th (weather pending). Traffic control will be in place during construction. Please drive safe through construction zones

 

 

Hallmark Dr, Benson Way, Saint James Rd

March 18- March 22

8AM – 5PM

A wireless contractor will continue directional boring for installing new conduit, and other necessary work along these streets for a fiber optic upgrade project. Traffic control will be in place during construction.  Please drive safe through construction zones.

 

 

 

Carlmont Dr (Merry Moppet Preschool) 

March 18- March 22

9AM – 4PM

The Merry Moppet School project contractor will be constructing two new driveways on Carlmont Drive next week.  They will also saw-cut across Merry Moppet Lane to install a new crosswalk.  The parking lane will be closed along Carlmont Drive between 9AM to 4PM during the constructions.  Traffic control with flaggers will be implemented.  Two ways traffic will be maintained at all time.