Traffic Advisories

NNOWe understand your time is precious, so we are planning to provide you with up to date information so you have greater control over your drive, with insights that allow you to discover the best route so you can save time.  

We are bringing you the traffic advisory weekly updates on currently known roadway and related projects, and private utility work (based on street encroachment permits), to provide you an opportunity to look ahead, plan your travel times and check delays due to various street activities.   

 

  South Road/Ralston Avenue Intersection Project
  March 12 - August 31
  8:00AM - 5:00PM

       
 

The contractor will continue to install conduit for the traffic signals, work on the sidewalk improvements on the northwest corner of the intersection and along the north side of Ralston Avenue, and form up the curb ramp at South Road. Lane closures are expected on Ralston Avenue between 9am-3pm. Shoulder work is permitted between 8am-5pm.

Next Wednesday 8/22 PG&E is scheduled to lower that vault to grade. I assume they will need a lane. If PG&E comes out and does this we will pour the remaining concrete around the vault on Thursday, August 23, in which we will need a lane. During construction, one of the following lanes may be closed - traffic control/flaggers will be in place:

#2 West Bound Lane on Ralston Ave

#2 East Bound Lane on Ralston Ave

 

  Sanitary Sewer and Water Rehabilitation Project
  May 29- Fall 2018
  8:00AM - 5:00PM

As part of City’s ongoing sewer capital replacement program to tackle aging and deteriorated sanitary sewer infrastructure and Mid-Peninsula Water District (MPWD) capital improvement program, the City has contracted with K.J. Woods to rehabilitate defective and failing sewer and water mains located throughout the City. The project also includes manhole rehabilitation, sewer lateral reconnections, water valves, water service laterals, and fire hydrants. Construction of the project will begin on May 29, 2018 and is expected to be completed by Fall 2018.

Davey Glen Road:

Contractor will begin pipe bursting the new sewer main, connect laterals, and perform manhole repairs. Davey Glen Road will be closed to through traffic at El Camino Real and Middle Road from 8am to 5pm Monday through Friday. Flaggers will be used for mobilization assistance.

Francis Avenue:

KJ Woods will be performing tie in connections and service transfers of the Water Main (WM).  Soon followed by Trench Pavement restoration. This work is expected to last from Wednesday, August 22, 2018 to Friday, August 24, 2018

Belburn:

KJ Woods will be performing tie in connections and service transfers of the Water Main (WM).  Soon followed by Trench Pavement restoration. This work is expected to last from Monday, August 20, 2018 to Tuesday, August 21, 2018

Villa Avenue (Easement):

Contractor will be doing restoration work in the easement from the pipe bursting of the sewer main and finishing up work from previous week. Belburn Drive will be closed to through traffic between Academy Avenue and Villa Avenue starting Monday, July 23, 2018 from 8am – 5pm. Flaggers will be used for mobilization assistance. 

 

 

Tahoe Intersection Signal Project 

June 25-Fall 2018

9:00AM -3:00PM

Next Week's activities for The Ralston Middle School Roadway Improvement Project are drilling for signal foundations on South side of Ralston (one traffic lane will be closed for this activity), continue to place and compact AB for new curb and gutter along Ralston Ave (One traffic lane will be close for this activity), install forms and pour concrete for new curb & gutter along Ralston Avenue, and place concrete for sidewalk and ADA ramps in front of school. Lane closures are expected along Ralston Avenue between 9am-3pm, and traffic will still be affected at the Tahoe Drive intersection as well.

Traffic control and flaggers will be in place as lane closures will be needed for these activities. 

 

Ralston Avenue Sewer Rehabilitation Project Phase II                                           

 August 20 -August 24

9:00AM -3:00PM

Ralston Avenue:

               

Express Plumbing Services will begin to potholing at the new proposed manhole station on Ralston Avenue (Station 10004+00).  This work is scheduled to take place on Monday. August 20, 2018 and Tuesday, August 21, 2018 from 10:00 am – 2:00pm.

 

Express Plumbing Services will move forward with repairing the 27-foot spot repair (C5) with 10-inch HDPE pipe STA 202+73 TO 203+00. This work is scheduled to take place from Wednesday, August 22, 2018 to Friday August 24, 2018 from 9:00 am to 3:00pm.


 

 

600 El Camino Real Sewer Main Installation

July 13 - July 20

9:00AM -3:00PM

El Camino Real

Friday, 7/13 – Casey Construction (subcontractor for CHS Development) will be closing the #2 lane on El Camino Real between the hours of 9am-3pm to saw cut for sewer main installation for 600 El Camino Real development.

 

Monday, 7/16 thru Friday, 7/20 – Casey Construction will be closing the #2 lane on El Camino Real between the hours of 9am-3pm to install 400’ of new 8” sewer main, (2) manholes, and (1) lateral connection for 600 El Camino Real development. 

Traffic control will be in place.

 

 

 

 

 

Ralston Retaining Wall Repair Project

July 16-August 30

9:00AM -3:00PM

Contractor will be continuing to drill for the soldier piles for the wall repair up at Ralston Avenue at Pullman Ave. #2 West Bound lane closure expected all week between 8am-3:30pm with traffic control in place.

 

 

 

Anita Avenue -Repairs from Malcolm to El Camino Real

August 13-August 14

8:00AM -4:00PM

Public Works Street Division will be performing street repairs on Anita Avenue. Anita Avenue will be closed from Malcolm Avenue to El Camino Real. Detour signs will be posted and traffic control will be in place.